Jasmine Development Project

Status: Completed
Jacket Jasmine Load Out

Scope of Work

Construction engineering, procurement, fabrication, load-out and sea-fastening.

Project Description

​Realization of JASMINE WHP, JLQ & JRP substructures - nr. 3 Jacket and Piles

Technical Details

Main feature WHP Four-legged jacket 5.300 Te (Weight)
Nr.9 skirt piles  3.800 Te (Weight)
JRP Four-legged jacket 5.600 Te (Weight)
Nr.8 skirt piles  3.400 Te (Weight)
JLQ Four-legged jacket 3.400 Te (Weight)
Nr. 4 skirt piles  1.700 Te (Weight)