EPCIC8: FDBN F-Location Debottlenecking Project

EPCIC8: FDBN F-Location Debottlenecking Project

 

 

Status: Completed

Client: North Oil Company (NOC)

Contractor: Rosetti Marino Qatar Branch


Scope of Work:

Provision of Engineering, Procurement, Construction, Installation, Commissioning and assistance to Start-up for brownfield upgrade scope of existing FA and FB facilities at F-Location

The Main Components are, but not limited to:

FA new Flare KO Drum module, including PSV’s & FKOD pumps.

Fabrication of FA 20” x 24” Pig launcher skid.

Fabrication of laydown deck extension at west end of FA Location.

Fabrication of deck extension and runway beam for new FB 20” Riser ESDV valve.

Topside pipeline interface for 20” LP wet gas pipeline from FA Pig launcher via FA-FB bridge and FB 20” Riser ESDV connecting to top of riser.

Upgrade of FA flare system with new header and PSV’s.

Removal of flow restriction orifice at AB platform, crude manifold.

Moreover, further Sub Components modifications and installation are included as part of the scope of work.


Location: Qatar – Al-Shaheen field 

Fabrication Site: Milaha Yard, Mesaieed (Qatar)

Date of award: June 2021

Date of delivery: April 2024