The jacket weighing around 900t was transported from the shipyard to the installation site using the HLV Aegir hook belonging to HEEREMA Marine Contractors. Therefore, it was not necessary to use a cargo barge and a tug or to install/manufacture expensive grillages and lashings.
This choice allowed the verticalisation and positioning of the Jacket in just a few hours from its arrival at the site.
The Living Quarter structure weighing 3,000t was transported on the deck of HLV Aegir (DP Class 3 – split load grillage / main crane) from the construction site to the installation site where it was installed only 6 hours after its departure.
Congratulation to the whole project team!