Last 12 September 2020, the Tolmount platform sailed away from Rosetti Piomboni Yard in Marina di Ravenna to reach its final destination, the Tolmount Main Field located in the North Sea.
Once it arrives, installation and hook-up activities will start.
The platform, designed and developed entirely in Italy, with the best technologies to operate NUI (normally unmanned installation) and with low carbon emissions, will handle wet gas production from five platform wells, providing energy to tens of thousands of families in the UK.
The project involved more than 1,100,000 manhours, performed LTI free, for a duration of 26 months.
A special thanks to Premier Oil for the trust placed in us and to the entire Rosetti Marino team who accepted the challenge and achieved the goal.